Changing a road from flexible asphalt to rigid concrete is more than a change of surface. It requires a close reading of the ground, the movement of water and the way loads are transferred through the pavement. Our brief for the Abeokuta–Iboro–Ilaro corridor brought those questions together.
Specialist hydrological assessment, drainage design and concrete pavement optimisation.
01 / The setting
Reading the landscape beyond the carriageway.
The Abeokuta–Iboro–Ilaro Expressway in Ogun State formed the setting for a specialist civil engineering scope. The brief concerned the move from flexible pavement to rigid concrete construction, alongside the drainage measures needed to support the road over its service life.
A road corridor receives water from a much wider area than its paved footprint. Understanding the surrounding catchments is therefore part of understanding the pavement itself. Runoff, culvert capacity and the condition of the supporting ground are connected design considerations.
02 / Our contribution
Turning terrain data into drainage decisions.
SPV’s scope used satellite terrain data and historical rainfall information to analyse the catchments affecting the route. Hydraulic models translated that information into an assessment of how water could move towards, across and away from the road corridor.
The drainage work covered networks, culverts and catchment areas. Reviewing these elements together helps the design team consider upstream flows alongside the capacity and position of crossing structures. The resulting models provide a technical basis for coordinating drainage with the highway design.
03 / Design attention
A pavement strategy grounded in its setting.
The pavement work focused on concrete slab thickness optimisation. Thickness is one of the decisions that connects structural demand, material use and the performance of the supporting layers. It needs to be considered with the ground conditions and water-management strategy rather than selected as a stand-alone specification.
Subgrade soil stabilisation specifications addressed the foundation beneath the road. Together with the hydraulic modelling and slab schedules, these inputs supported a coordinated approach to pavement durability. The objective was to make the design assumptions clear and translate them into requirements a construction team could use.